As of August 2024, the Hoa Phat Dung Quat 2 Iron and Steel Production Complex project has completed 80% of Phase 1 and 50% of Phase 2
Phase 1 is expected to complete the installation of HRC steel production line equipment by mid-September 2024. Following this, the manufacturer will conduct cold testing and equipment calibration. Based on the current progress, the first hot trial products are anticipated by the end of 2024.
IMP Viet Nam Trading Joint Stock Company is the exclusive supplier of the entire volume of Starduct-branded cable tray systems (TMC) for this project. Alongside the accelerated construction timeline of Hoa Phat Group’s project, IMP’s production and supply of Starduct cable tray systems (TMC) have surpassed the initial schedule by 12 months. As of the end of August 2024, IMP has supplied nearly 3,000 tons of Starduct cable tray systems (TMC) for this Project.
By collaborating with the project investor, IMP has been highly regarded by the client for its financial capacity, technical solutions, and production capabilities of Starduct cable tray systems (TMC), contributing to the Project’s successful completion ahead of targets.